Each week Kempsey Shire Council prepares a report detailing the work that our infrastructure crews have carried out in the week prior and plan to deliver in the coming week.
LAST UPDATE: Thursday 3 April 2025
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Regional Roads - Construction, Rehabilitation & Maintenance
Plummers Lane, Clybucca |
Plummers Lane, Clybucca |
Line marking |
Line marking |
Deferred |
To commence |
Rural Roads - Construction, Rehabilitation & Maintenance
Nulla Nulla Creek Road, Bellbrook |
|
Nurse Kirkpatrick Bridge Approach Construction |
|
Complete |
|
Urban Local Roads - Construction, Rehabilitation & Maintenance
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Asphalting Program
Works currently in planning. To be delivered at a later date. |
Heavy Patching Program
Armidale Road (3 Locations) |
Armidale Road (3 Locations) |
Edging of pavement |
Edging of pavement |
10% complete |
To continue |
Placement of gravel |
Placement of gravel |
10% complete |
To continue |
Sealed Roads - Resealing Program
Ocean Street |
|
Resealing |
|
Complete |
|
Gilbert Cory Street |
|
Resealing |
|
Complete |
|
Marlin Drive |
|
Resealing |
|
Complete |
|
Arakoon Road |
Arakoon Road |
Resealing |
Resealing |
Deferred |
To commence |
Sealed Roads - Maintenance Program
Flocon Program |
Flocon Program |
30% complete |
To continue |
Reactive Pothole Maintenance |
Reactive Pothole Maintenance |
Ongoing |
Ongoing |
Reflect Defects |
Reflect Defects |
Ongoing |
Ongoing |
Sealed Roads - Line Marking Program
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Unsealed Gravel Re-Sheeting Program
Chain O Ponds Road |
Chain O Ponds Road |
Placement of gravel |
Placement of gravel |
30% complete - deferred |
To continue |
Unsealed Roads - Maintenance Grading Program
Toose Road |
Toose Road |
50% complete - deferred |
To continue |
Kinchela Creek Right Bank Road |
Kinchela Creek Right Bank Road |
75% complete - deferred |
To complete |
Kinchela Creek Left Bank Road |
Kinchela Creek Left Bank Road |
75% complete - deferred |
To complete |
Darkwater Street |
Darkwater Street |
Deferred |
To commence |
Carrai Road |
Carrai Road |
50% complete - deferred |
To continue |
Church Lane |
Church Lane |
Deferred |
To commence |
Two Hills Lane |
Two Hills Lane |
Deferred |
To commence |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Roadside Slashing and Vegetation Control
Stuarts Point Area |
|
Complete |
|
Armidale Road |
Armidale Road |
10% complete |
To continue |
Bellbrook Streets |
Bellbrook Streets |
5% complete |
To continue |
Nulla Nulla Creek Road |
Nulla Nulla Creek Road |
Deferred |
To commence |
West Kempsey Area |
West Kempsey Area |
30% complete |
To continue |
Tree Mulching Program
Works currently in planning. To be delivered at a later date. |
Street Sweeping
Weekly Routine Maintenance Schedule |
Weekly Routine Maintenance Schedule |
Ongoing |
Ongoing |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Kerb and Gutter Program
Polwood Street, West Kempsey |
Polwood Street, West Kempsey |
Installation of kerb and gutter |
Installation of kerb and gutter |
5% complete |
To continue |
Capital Works Program
Edgar Street, Frederickton |
Edgar Street, Frederickton |
Excavation of pavement |
|
Deferred |
|
|
Preparation for seal |
|
To commence |
Footpath Program
|
Smith Street, Kempsey (South East Corner) |
|
Concrete honing and sealing |
|
To commence in April |
Smith Street, Kempsey (North East Corner) |
Smith Street, Kempsey (North East Corner) |
Replacement of pavers |
Replacement of pavers |
50% complete - deferred |
Deferred |
CWA Hall Footpath and Disabled Parking |
CWA Hall Footpath and Disabled Parking |
20% complete - deferred |
To continue |
Stormwater Drainage Program
Gregory Street, South West Rocks |
Gregory Street, South West Rocks |
|
Asphalting |
|
To commence in May |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Signs
Mitchell Street |
Mitchell Street |
Signs, splitter island and pavement markers |
Signs, splitter island and pavement markers |
50% complete - deferred |
To continue |
Killuke Crescent |
Killuke Crescent |
Signs and pavement markings |
Signs and pavement markings |
50% complete - deferred |
To continue |
Rankine Street |
Rankine Street |
Signage and pavement markings |
Signage and pavement markings |
10% complete - deferred |
To continue |
Sportsman Way |
Sportsman Way |
Signage and pavement markings |
Signage and pavement markings |
10% complete - deferred |
Deferred |
Horseshoe Bay Car Park |
Horseshoe Bay Car Park |
Signage |
Signage |
In progress |
To continue |
Smith Street |
Smith Street |
Signage and pavement markings |
Signage and pavement markings |
In progress |
To continue |
Harold Walker Avenue |
Harold Walker Avenue |
Pavement markings |
Pavement markings |
In progress |
To continue |
Belle O'Connor Street |
Belle O'Connor Street |
Signage |
Signage |
In progress |
To continue |
Wide Street |
|
Signage and bollards |
|
Complete |
|
River Street |
River Street |
Relocation of signage |
Relocation of signage |
In progress |
To continue |
Various Bus Stops |
Various Bus Stops |
Installation of J pole signs |
Installation of J pole signs |
In progress |
To continue |
Linsday Noonan Drive |
Linsday Noonan Drive |
Signage |
Signage |
In progress |
To continue |
Arakoon Road |
Arakoon Road |
Signage |
Signage |
In progress |
To continue |
Point Plomer Road |
|
Signage |
|
Complete |
|
Plummers Lane |
|
Relocation of signage |
|
Complete |
|
Reserve off Arthur Street |
Reserve off Arthur Street |
Signage |
Signage |
In progress |
To continue |
Customer requests/Maintenance |
Customer requests/Maintenance |
Ongoing |
To continue |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Bridge Replacement Program
Nurse Kirkpatrick Bridge
|
|
Removal of old structure |
|
Complete |
|
Wharves, Jetties and Footbridge Program
Smithtown Wharf Replacement, Smithtown |
Smithtown Wharf Replacement, Smithtown |
Wharf component installation |
Wharf component installation |
10% complete - deferred |
To continue |
Gladstone Wharf Replacement, Gladstone |
Gladstone Wharf Replacement, Gladstone |
Abutment installation |
Abutment installation |
Deferred |
Deferred |
Parks and Facilities Program
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Sporting Infrastructure
Works currently in planning. To be delivered at a later date. |
Sports Field Maintenance
Works currently in planning. To be delivered at a later date. |
Open Spaces Program
|
Willow Street, Crescent Head |
|
Replacement of bollards |
|
To commence |
|
Replacement of picnic shelter |
|
To commence |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Works currently in planning. To be delivered at a later date.
|
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Everinghams Lane, Frederickton |
Everinghams Lane, Frederickton |
Redefining of drain and pavement |
Redefining of drain and pavement |
5% complete - deferred |
Deferred |
Riverside Park, Kempsey - Work Area 3 (under bridge) |
Riverside Park, Kempsey - Work Area 3 (under bridge) |
Stabilisation |
Stabilisation |
Installation of sheet piles |
Installation of sheet piles |
90% complete |
To continue |
Installation of capping beam |
Installation of capping beam |
20% complete - deferred |
To complete |
Riverside Park, Kempsey - Work Area 4 (north of bridge) |
Riverside Park, Kempsey - Work Area 4 (north of bridge) |
Stabilisation |
Stabilisation |
Installation of circular hollow sections - (CHS) |
Installation of circular hollow sections - (CHS) |
50% complete - deferred |
To continue |
Installation of capping beam |
Installation of capping beam |
55% complete - deferred |
To continue |
Shire Wide |
Shire Wide |
Stormwater drainage maintenance |
Stormwater drainage maintenance |
Ongoing |
Ongoing |
Shire Wide - Minor Maintenance Response |
Shire Wide - Minor Maintenance Response |
Customer requests |
Customer requests |
Ongoing |
Ongoing |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.