Each week Kempsey Shire Council prepares a report detailing the work that our infrastructure crews have carried out in the week prior and plan to deliver in the coming week.
LAST UPDATE: Thursday 17 April 2025
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Regional Roads - Construction, Rehabilitation & Maintenance
Plummers Lane, Clybucca |
Plummers Lane, Clybucca |
Line marking |
Line marking |
Deferred |
To commence |
Rural Roads - Construction, Rehabilitation & Maintenance
Nulla Nulla Creek Road, Bellbrook |
Nulla Nulla Creek Road, Bellbrook |
Cleaning and decommissioning of site |
Cleaning and decommissioning of site |
Deferred |
To commence |
Urban Local Roads - Construction, Rehabilitation & Maintenance
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Asphalting Program
Works currently in planning. To be delivered at a later date. |
Heavy Patching Program
Armidale Road (3 Locations) |
Armidale Road (3 Locations) |
Edging of pavement |
|
Complete |
|
Placement of gravel |
|
Complete |
|
|
Sealing of pavement |
|
To commence |
Spooners Avenue |
Spooners Avenue |
Drainage works |
Drainage works |
50% complete |
Deferred |
Sealed Roads - Resealing Program
Works currently in planning. To be delivered at a later date. |
Sealed Roads - Maintenance Program
Flocon Program |
Flocon Program |
30% complete - deferred |
Deferred |
Sherwood Road |
|
Complete |
|
Armidale Road |
|
Complete |
|
Point Plomer Road |
|
Complete |
|
Victor Supple Place |
|
Complete |
|
Summer Island Road |
|
Complete |
|
Euroka Road |
|
Complete |
|
Marys Bay Road |
|
Complete |
|
Reactive Pothole Maintenance |
Reactive Pothole Maintenance |
Ongoing |
Deferred |
Reflect Defects |
Reflect Defects |
Ongoing |
Deferred |
Sealed Roads - Line Marking Program
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Unsealed Gravel Re-Sheeting Program
Chain O Ponds Road |
Chain O Ponds Road |
Placement of gravel |
Placement of gravel |
95% complete |
Deferred |
Unsealed Roads - Maintenance Grading Program
Darkwater Street |
Darkwater Street |
Deferred |
Deferred |
Carrai Road |
Carrai Road |
60% complete - deferred |
Deferred |
Upper Smiths Creek Road |
Upper Smiths Creek Road |
95% complete |
Deferred |
Old Coast Road |
Old Coast Road |
Deferred |
Deferred |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Roadside Slashing and Vegetation Control
Plummers Lane |
Plummers Lane |
50% complete |
To complete |
Armidale Road |
Armidale Road |
10% complete - deferred |
To continue |
Bellbrook Streets |
|
Complete |
|
Nulla Nulla Creek Road |
|
Complete |
|
|
Summer Island Road |
|
To commence |
|
Hickeys Creek Road |
|
To commence |
|
Toorooka Road |
|
To commence |
West Kempsey Area |
West Kempsey Area |
70% complete |
To continue |
Tree Mulching Program
Works currently in planning. To be delivered at a later date. |
Street Sweeping
Weekly Routine Maintenance Schedule |
Weekly Routine Maintenance Schedule |
Ongoing |
Ongoing |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Kerb and Gutter Program
Works currently in planning. To be delivered at a later date. |
Capital Works Program
Edgar Street, Frederickton |
Edgar Street, Frederickton |
Stabilising of pavement |
|
Complete |
|
|
Sealing of pavement |
|
To commence |
Baker Drive, Crescent Head |
Baker Drive, Crescent Head |
Car Park/Footpath Works |
Car Park/Footpath Works |
30% complete |
Deferred |
Footpath Program
|
Smith Street, Kempsey (South East Corner) |
|
Concrete honing and sealing |
|
To commence in April |
Smith Street, Kempsey (North East Corner) |
Smith Street, Kempsey (North East Corner) |
Replacement of pavers |
Replacement of pavers |
60% complete - deferred |
Deferred |
Stormwater Drainage Program
Gregory Street, South West Rocks |
Gregory Street, South West Rocks |
|
Asphalting |
|
To commence in May |
Stormwater Drainage Program
Various Locations |
|
Complete |
|
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Signs
Mitchell Street |
Mitchell Street |
Signs, splitter island and pavement markers |
Signs, splitter island and pavement markers |
90% complete |
Deferred |
Killuke Crescent |
Killuke Crescent |
Signs and pavement markings |
Signs and pavement markings |
50% complete - deferred |
To continue |
Rankine Street |
|
Signage and pavement markings |
|
Complete |
|
Sportsman Way |
|
Signage and pavement markings |
|
Complete |
|
Horseshoe Bay Car Park |
|
Signage |
|
Complete |
|
Smith Street |
Smith Street |
Signage and pavement markings |
Signage and pavement markings |
In progress |
To continue |
Harold Walker Avenue |
|
Pavement markings |
|
Complete |
|
River Street |
|
Relocation of signage |
|
Complete |
|
Various Bus Stops |
Various Bus Stops |
Installation of J pole signs |
Installation of J pole signs |
In progress |
To continue |
Linsday Noonan Drive |
|
Signage |
|
Complete |
|
Arakoon Road |
|
Signage |
|
Complete |
|
Reserve off Arthur Street |
|
Signage |
|
Complete |
|
Entry to Horseshoe Bay Car Park |
Entry to Horseshoe Bay Car Park |
Signage |
Signage |
In progress |
To continue |
Customer requests/Maintenance |
Customer requests/Maintenance |
Ongoing |
To continue |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Bridge Replacement Program
Works currently in planning. To be delivered at a later date. |
Wharves, Jetties and Footbridge Program
Smithtown Wharf Replacement, Smithtown |
Smithtown Wharf Replacement, Smithtown |
Wharf component installation |
Wharf component installation |
25% complete |
Deferred |
Gladstone Wharf Replacement, Gladstone |
Gladstone Wharf Replacement, Gladstone |
Abutment installation |
Abutment installation |
Deferred |
Deferred |
Parks and Facilities Program
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Sporting Infrastructure
Works currently in planning. To be delivered at a later date. |
Sports Field Maintenance
Works currently in planning. To be delivered at a later date. |
Open Spaces Program
Willow Street, Crescent Head |
Willow Street, Crescent Head |
Replacement of bollards |
Replacement of bollards |
Deferred |
Deferred until after school holidays |
Replacement of picnic shelter |
Replacement of picnic shelter |
Deferred |
Deferred until after school holidays |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Works currently in planning. To be delivered at a later date.
|
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Works currently in planning. To be delivered at a later date. |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.
Works Achieved This Week |
Proposed Works Next Week |
Everinghams Lane, Frederickton |
Everinghams Lane, Frederickton |
Redefining of drain and pavement |
Redefining of drain and pavement |
5% complete - deferred |
Deferred |
Riverside Park, Kempsey - Work Area 3 (under bridge) |
Riverside Park, Kempsey - Work Area 3 (under bridge) |
Stabilisation |
Stabilisation |
Installation of sheet piles |
Installation of sheet piles |
90% complete - deferred |
Deferred |
Installation of capping beam |
Installation of capping beam |
25% complete - deferred |
Deferred |
Saltwater Creek Outlet Opening, South West Rocks |
|
Opening of creek to ocean |
|
Complete |
|
Riverside Park, Kempsey - Work Area 4 (north of bridge) |
Riverside Park, Kempsey - Work Area 4 (north of bridge) |
Stabilisation |
Stabilisation |
Installation of tie rods |
Installation of tie rods |
Deferred |
Deferred |
Shire Wide |
Shire Wide |
Reactive Stormwater drainage maintenance |
Reactive Stormwater drainage maintenance |
Ongoing |
Deferred |
Shire Wide - Minor Maintenance Response |
Shire Wide - Minor Maintenance Response |
Customer requests |
Customer requests |
Ongoing |
Ongoing |
Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.