Weekly works update

Each week Kempsey Shire Council prepares a report detailing the work that our infrastructure crews have carried out in the week prior and plan to deliver in the coming week.

Scheduled work is merely an indication of intentions, not a guarantee of work being carried out as factors including weather and unexpected needs can impact priorities.

LAST UPDATE: Thursday 21 November 2024 

Road Construction and Maintenance Program 

Works Achieved This Week Proposed Works Next Week
Road Construction and Maintenance Program
Regional Roads – Construction, Rehabilitation & Maintenance
Plummers Lane, Jerseyville Plummers Lane, Jerseyville
Sealing
Complete
Line marking
To commence
Heavy Patching Program
Arakoon Road Arakoon Road
Sealing
Complete
Line marking
To commence
Sealed Roads – Resealing Program
Marys Bay Road Marys Bay Road
Edging
Complete
Spray sealing
To commence
Armidale Road Armidale Road
Edging
Complete
Spray sealing
To commence
Hickeys Creek Road Hickeys Creek Road
Edging Edging
Deferred To commence
Spray sealing
To commence
Sealed Roads – Maintenance Program
Flocon Program Flocon Program
70% complete To continue
Reactive Pothole Maintenance Reactive Pothole Maintenance
Ongoing Ongoing
Reflect Defects Reflect Defects
Ongoing Ongoing
Sealed Roads – Line Marking Program
Smithtown Road
Complete
Macleay Valley Way
To commence
Second Lane
To commence
Cochrane Street
To commence
Sea Street
To commence
Unsealed Gravel Re-sheeting Program
Pipers Creek Road
To commence
Unsealed Roads – Maintenance Grading Program
Maria River Road Maria River Road
50% complete - deferred Deferred
Turners Flat Road Turners Flat Road
Deferred To commence
Five Day Creek Road Five Day Creek Road
40% complete To continue
Spooners Avenue Spooners Avenue
90% complete Deferred
Pola Creek Road Pola Creek Road
Deferred To commence
Roadside Slashing and Vegetation Control Program
Armidale Road Armidale Road
90% complete To complete
Plummers Lane
Complete
Kundabung Area Kundabung Area
5% complete - deferred Deferred
West Kempsey Area West Kempsey Area
50% complete - deferred To continue
South Kempsey Area South Kempsey Area
80% complete - deferred To continue
Crescent Head Road at Corduroy
Complete
Tree Mulching Program
Belmore River Right Bank Road Belmore River Right Bank Road
Deferred Deferred
Sherwood Road Sherwood Road
Deferred Deferred
Street Sweeping
Weekly Routine Maintenance Schedule Weekly Routine Maintenance Schedule
Ongoing Ongoing
Civil Construction Program
Capital Works Program
Edgar Street, Frederickton - Stage 3 Parkins Place to North Street
Installation of kerb and gutter
Complete
Edgar Street, Frederickton - Stage 4 North Street to William Street Edgar Street, Frederickton - Stage 4 North Street to William Street
Installation of stormwater drainage Installation of stormwater drainage
90% complete To complete
Installation of kerb and gutter Installation of kerb and gutter
40% complete To continue
Installation of driveways
To commence
Edgar Street, Frederickton - Stage 5 William Street to Christmas Street
Installation of stormwater drainage
To commence
Footpath Program
Smith Street, Kempsey (East) Smith Street, Kempsey (East)
Replacement of pavers Replacement of pavers
50% complete To continue
Cardwell Street, Arakoon Cardwell Street, Arakoon
Installation of walkway bridges Installation of walkway bridges
5% complete To continue
Stormwater Drainage Program
Jerseyville Drainage Repairs
Installation of pits, pipes and headwall
Complete
Stormwater drain clearing
Complete
Traffic Facilities
Signs
Mitchell Street, South West Rocks Mitchell Street, South West Rocks
Signs, splitter island and pavement markers Signs, splitter island and pavement markers
50% complete - deferred To continue
Sherwood Road, Sherwood Sherwood Road, Sherwood
Signs Signs
In progress To continue
Killuke Crescent, Crescent Head Killuke Crescent, Crescent Head
Signs and pavement markings Signs and pavement markings
50% complete - deferred To continue
Secombs Lane, Hickeys Creek
Installation of flood signage and depth indicator
Complete
Rankine Street, Crescent Head Rankine Street, Crescent Head
Signage and pavement markings Signage and pavement markings
In progress To continue
Gregory Street, South West Rocks x 2 Gregory Street, South West Rocks x 2
Signage Signage
50% complete To continue
Sportsman Way, South West Rocks Sportsman Way, South West Rocks
Signage and pavement markings Signage and pavement markings
In progress To continue
Smith Street, Kempsey
Relocation of signage
Complete
Horseshoe Bay Car Park, South West Rocks Horseshoe Bay Car Park, South West Rocks
Signage Signage
In progress To continue
Upper Belmore River Right Bank Road, Belmore River
Signage
Complete
Point Plomer Road, Crescent Head x 2
Signage
Complete
Smith Street, Kempsey Smith Street, Kempsey
Signage and pavement markings Signage and pavement markings
In progress To continue
East Kempsey Cemetery, East Kempsey East Kempsey Cemetery, East Kempsey
Signage Signage
In progress To continue
Harold Walker Avenue, West Kempsey Harold Walker Avenue, West Kempsey
Pavement markings Pavement markings
In progress To continue
Toms Gully Road, Hickeys Creek
Signage
Complete
Euroka Cemetery, Euroka
Signage
Complete
Bellbrook Cemetery, Bellbrook
Signage
Complete
Stuarts Point Cemetery, Stuarts Point
Signage
Complete
Stuart Street, Kempsey
Signage
Complete
Baker Drive, Crescent Head
Signage
Complete
Verge Lane, Kempsey
Signage
Complete
Marsh Street, West Kempsey Marsh Street, West Kempsey
Signage Signage
In progress To continue
Customer requests/Maintenance Customer requests/Maintenance
Ongoing To continue
Wharves, Jetties and Footbridge Program
Smithtown Wharf Replacement, Smithtown Smithtown Wharf Replacement, Smithtown
Abutment installation Abutment installation
20% complete To continue
Gladstone Wharf Replacement, Gladstone Gladstone Wharf Replacement, Gladstone
Abutment installation Abutment installation
Deferred To commence
Open Spaces Program
Grassy Head Holiday Park, Grassy Head Grassy Head Holiday Park, Grassy Head
Public Toilet Renovations Public Toilet Renovations
Installation of trusses, framing, lintels & posts
Complete
Replacement of roof & gutter Replacement of roof & gutter
30% complete To continue
Painting
To commence
Horseshoe Bay Playground, South West Rocks
Site establishment
To commence
Fencing
To commence
Repairing of playground
To commence
Kemp Street Sports Fields, West Kempsey Kemp Street Sports Fields, West Kempsey
Sports Building Renovations Sports Building Renovations
Demolition Demolition
Complete To complete
Waterproofing Waterproofing
50% complete To complete
Tiling
To commence
Additional Projects and Other Works
Everinghams Lane, Frederickton Everinghams Lane, Frederickton
Redefining of drain and pavement Redefining of drain and pavement
5% complete - deferred To continue
Arakoon Cemetery, Arakoon Road, Arakoon Arakoon Cemetery, Arakoon Road, Arakoon
Improvements and Upgrade Improvements and Upgrade
Installation of pavement Installation of pavement
30% complete To continue
Installation of kerb Installation of kerb
10% complete To continue
Installation of footpaths Installation of footpaths
10% complete To continue
Shire Wide Shire Wide
Stormwater drainage maintenance Stormwater drainage maintenance
Ongoing Ongoing
Shire Wide - Minor Maintenance Response Shire Wide - Minor Maintenance Response
Customer requests Customer requests
Ongoing Ongoing

 

 

Civil Construction Program

Works Achieved This Week Proposed Works Next Week

Kerb and Gutter Program

Works currently in planning. To be delivered at a later date.
Capital Works Program
Edgar Street, Frederickton - Stage 3 Parkins Place to North Street Edgar Street, Frederickton - Stage 3 Parkins Place to North Street
Installation of kerb and gutter Installation of kerb and gutter
90% complete - deferred To continue
Edgar Street, Frederickton - Stage 4 North Street to William Street Edgar Street, Frederickton - Stage 4 North Street to William Street
Installation of stormwater drainage Installation of stormwater drainage
70% complete - deferred To continue
Installation of kerb and gutter Installation of kerb and gutter
35% complete To continue
Footpath Program
Smith Street, Kempsey (East) Smith Street, Kempsey (East)
Replacement of pavers Replacement of pavers
30% complete To continue
Cardwell Street, Arakoon Cardwell Street, Arakoon
Installation of footpath
Complete
Installation of walkway bridges
To commence
Stormwater Drainage Program
Jerseyville Drainage Repairs Jerseyville Drainage Repairs
Installation of pits, pipes and headwall Installation of pits, pipes and headwall
90% complete To continue
Stormwater drain clearing
To commence

 

Traffic Facilities

Works Achieved This Week Proposed Works Next Week
Signs
Mitchell Street, South West Rocks Mitchell Street, South West Rocks
Signs, splitter island and pavement markers Signs, splitter island and pavement markers
50% complete - deferred To continue
Sherwood Road, Sherwood Sherwood Road, Sherwood
Signs Signs
In progress To continue
Killuke Crescent, Crescent Head Killuke Crescent, Crescent Head
Signs and pavement markings Signs and pavement markings
50% complete - deferred To continue
Secombs Lane, Hickeys Creek Secombs Lane, Hickeys Creek
Installation of flood signage and depth indicator Installation of flood signage and depth indicator
In progress To continue
Rankine Street, Crescent Head Rankine Street, Crescent Head
Signage and pavement markings Signage and pavement markings
In progress To continue
Gregory Street, South West Rocks x 2 Gregory Street, South West Rocks x 2
Signage Signage
In progress To continue
Sportsman Way, South West Rocks Sportsman Way, South West Rocks
Signage and pavement markings Signage and pavement markings
In progress To continue
Smith Street, Kempsey Smith Street, Kempsey
Relocation of signage Relocation of signage
In progress To continue
Horseshoe Bay Car Park, South West Rocks Horseshoe Bay Car Park, South West Rocks
Signage Signage
In progress To continue
Upper Belmore River Right Bank Road, Belmore River Upper Belmore River Right Bank Road, Belmore River
Signage Signage
In progress To continue
Point Plomer Road, Crescent Head x 2 Point Plomer Road, Crescent Head x 2
Signage Signage
50% complete To continue
Smith Street, Kempsey Smith Street, Kempsey
Signage and pavement markings Signage and pavement markings
In progress To continue
East Kempsey Cemetery, East Kempsey East Kempsey Cemetery, East Kempsey
Signage Signage
In progress To continue
Harold Walker Avenue, West Kempsey Harold Walker Avenue, West Kempsey
Pavement markings Pavement markings
In progress To continue
Toms Gully Road, Hickeys Creek Toms Gully Road, Hickeys Creek
Signage Signage
In progress To continue
Euroka Cemetery, Euroka Euroka Cemetery, Euroka
Signage Signage
In progress To continue
Bellbrook Cemetery, Bellbrook Bellbrook Cemetery, Bellbrook
Signage Signage
In progress To continue
Stuarts Point Cemetery, Stuarts Point Stuarts Point Cemetery, Stuarts Point
Signage Signage
In progress To continue
Stuart Street, Kempsey Stuart Street, Kempsey
Signage Signage
In progress To continue
Baker Drive, Crescent Head Baker Drive, Crescent Head
Signage Signage
In progress To continue
Verge Lane, Kempsey Verge Lane, Kempsey
Signage Signage
In progress To continue
Marsh Street, West Kempsey Marsh Street, West Kempsey
Signage Signage
In progress To continue
Customer requests/Maintenance Customer requests/Maintenance
Ongoing To continue

 

Bridge Infrastructure Program

Works Achieved This Week Proposed Works Next Week
Bridge Replacement Program
Works currently in planning. To be delivered at a later date.
Wharves, Jetties and Footbridge Program
Smithtown Wharf Replacement, Smithtown Smithtown Wharf Replacement, Smithtown
Abutment installation Abutment installation
Deferred To commence
Gladstone Wharf Replacement, Gladstone Gladstone Wharf Replacement, Gladstone
Abutment installation Abutment installation
Deferred To commence
Parks and Facilities Program
Works currently in planning. To be delivered at a later date.

 

Sporting Infrastructure Program

Works Achieved This Week Proposed Works Next Week
Sporting Infrastructure
Works currently in planning. To be delivered at a later date.
Sports Field Maintenance
Works currently in planning. To be delivered at a later date.
Open Spaces Program
Grassy Head Holiday Park, Grassy Head Grassy Head Holiday Park, Grassy Head
Public Toilet Renovations Public Toilet Renovations
Demolition
Complete
Installation of trusses, framing, lintels & posts Installation of trusses, framing, lintels & posts
50% complete To complete
Replacement of roof & gutter
To commence
Kemp Street Sports Fields, West Kempsey Kemp Street Sports Fields, West Kempsey
Sports Building Renovations Sports Building Renovations
Demolition Demolition
75% complete To complete
Waterproofing
To commence

 

Flood mitigation works

Works Achieved This Week Proposed Works Next Week
Flood Mitigation Maintenance
Works currently in planning. To be delivered at a later date.
Riverbank Rock Protection Program
Works currently in planning. To be delivered at a later date.

 

 Additional Projects and Other Works

Works Achieved This Week Proposed Works Next Week
Everinghams Lane, Frederickton Everinghams Lane, Frederickton
Redefining of drain and pavement Redefining of drain and pavement
5% complete - deferred To continue
Arakoon Cemetery, Arakoon Road, Arakoon Arakoon Cemetery, Arakoon Road, Arakoon
Improvements and Upgrade Improvements and Upgrade
Stripping and tree clearing
Complete
Installation of pavement Installation of pavement
10% complete To continue
Installation of drainage
Complete
Installation of kerb
To commence
Installation of footpaths
To commence
Killick Creek, Crescent Head
Creek outlet realignment
Complete
Shire Wide Shire Wide
Stormwater drainage maintenance Stormwater drainage maintenance
Ongoing Ongoing
Shire Wide - Minor Maintenance Response Shire Wide - Minor Maintenance Response
Customer requests Customer requests
Ongoing Ongoing