An update on the Toose Road landslip: edition 15

Published on 11 August 2022

Kempsey Shire Council has committed to providing regular updates to residents and landowners directly impacted by the landslip on Toose Road.  

Update to geotechnical advice on the Landslip  

The significant repair works required at the slip site, alongside the unfavourable geotechnical conditions were discussed at length during the community meeting held on the 20th of July 2022. The repair of the slip was included as a potential long-term option, however when considered against other options presented it was considered as a low viability option. Further discussion on the long-term repair options can be found below. 

Construction update - short term access  

A summary of progress relating to the short-term access is provided below: 

  • Cut 1, Cut 2 and the Ridge Trail are complete.  

Note, the team that were working on Fifes Creek Road are now working on improving the short-term access road by battering the cutting faces, improving the gravel surface and placing a bunded wall for safety.  

  • Cut 3 is the most complex cut and will join an existing cut from the Telstra Tower – Toose Road trail. This cut is now approximately 97% established. Approximately 30m of rock remains to be removed and requires specialist contractors to drill and blast the hard rock. Achievements this week include: 

  • As per the previous update, approvals are now in place to proceed with the required drill and blast process. 

  • Specialist contractors have established to site and have commenced drilling works (see photo attached). 

  • The first blast is scheduled for Monday and Tuesday (15th and 16th of August). 

 

 

 

Council staff have completed resheeting, corner improvement and vegetation works on Fifes Creek Road to ensure that the alternate route includes acceptable conditions for access into Kempsey. Further works to be delivered include the installation of cattle grids, signage, and concrete water crossings. 

 

Due to the slow progress with Cut 3, advice on the opening timeframe has been delayed as per previous updates. An opening timeframe will be shared with the community once the rock has been removed from the top of cut 3. Please note that initially movement may be restricted to essential or emergency movements only.  

 

Investigation update – long term access  

As advised at the recent community meeting, the long-term reinstatement of a publicly accessible road is likely to take in the order of two years.  

 

Several options were presented to the community and were circulated with the weekly updates provided since the community meeting on the 20th of July. Meetings with impacted landholders has commenced and will continue until the preferred option is selected and announced. Thank you to those that have provided feedback, it is appreciated. 

 

 

 

Stock movements 

Council first approached Local Land Services (LLS) for assistance transporting and 

yarding isolated livestock on Wednesday 11 May. Following on-site inspections 

conducted by LLS on Wednesday 3 August 2022, Lauren Wilson is now your primary contact for all livestock welfare and movement enquiries: 

  • Lauren Wilson 

  • 0427 496 944 

  • lauren.wilson@lls.nsw.gov.au 

  • Call 1300 795 299 to contact Kempsey Local Land Service office from Monday to Friday 8.30am to 4.30pm 

Emergency provisions and supply  

Kate Macfarlane, Local Recovery Coordinator with Resilience NSW is coordinating 

the response for impacted residents: 

• Kate Macfarlane 

• 0498 324 677 

• kate.macfarlane@resilience.nsw.gov.au 

Flood recovery assistance 

Kate Macfarlane, Local Recovery Coordinator with Resilience NSW will be 

organising a community session in Bellbrook for assistance providers to attend. 

 

More information 

If you have any questions or issues please call Customer Service on 6566 3200 and ask to speak to the Readiness and Recovery Team. 

For more information head to www.ksc.pub/tooseroad   

If you are seeking any more information about Council head to www.kempsey.nsw.gov.au  

 

 

 

Improving Cut 1 (photo 1) 

 

 

Improving Cut 1 (photo 2) 

 

Drilling underway 

Toose Rd11Aug4.jpg