Weekly works schedule
Week ending 23 June 2017

Proposed schedule this week Work achieved this week Proposed schedule next week
Bridge construction/maintenance
  • Oil Terminal Footbridge, South West Rocks
    Rebuild bridge:
    - install joists
    - install handrail posts
    - install deck
    - install handrails
  • Oil Terminal Footbridge, South West Rocks
    Rebuild bridge:
    -  storm water drainage works
    Completed
    -  approach footpaths
    95% completed
    - decommission work site
    50% complete
  • Oil Terminal Footbridge, South West Rocks
    Rebuild bridge:
    - decommission worksite to complete
    -  footpath backfill to complete
  • Whalens Bridge
    - commence site establishment
    - remove existing bridge
    - repair concrete cancer in piles and pile cap
  • Nagles Falls Road bridge replacement
    Site establishment:
    - commence construction of side track
Flood mitigation maintenance
  • Various locations
    - drains maintenance - weed spraying
  • Various locations
    - Cox. Coral weed spraying
    75% completed
  • Various locations
    - complete Cox. Coral weed spraying
Drainage/kerb/footpath/drainage maintenance
  • Fernhill Crescent, Aldavilla
    Bestic Street, West Kempsey
    Collin Tait Avenue, West Kempsey
    Clarence Ryan Avenue, West Kempsey

    - pour kerb and gutter
  • Fernhill Crescent, Aldavilla
    - pavement repairs
    90% completed
  • Bestic Street, West Kempsey
    - kerb back fill
    Completed
    - pavement repairs
    75% completed
  • Collin Tait Avenue, West Kempsey
    - kerb back fill
    Completed
    - pavement repairs
    To complete
  • Clarence Ryan Avenue, West Kempsey
    - install new kerb
    Completed
    - back fill kerb
    25% completed
  • Fernhill Crescent, Aldavilla
    - seal road (pave liner) to complete
  • Bestic Street, West Kempsey
    Collin Tait Avenue, West Kempsey

    - pavement repairs to complete
  • Clarence Ryan Avenue, West Kempsey
    - back fill kerb to complete
    - pavement repairs to complete
Bitumen road resealing/maintenance
  • Stuarts Point area
    - pothole patching
  • Stuarts Point Road
    - heavy patching
  • Various locations
    - pothole repairs due to wet weather damage
  • Stuarts Point Road
    - heavy patching
    75% complete
  • Crescent Head Road
    South West Rocks Road

    - pothole repairs
    Completed
  • Stuarts Point area
    - pothole patching
  • Stuarts Point Road
    - continue heavy patching
  • Temagog Road
    Armidale Road

    - pothole repairs
Bitumen road construction/rehabilitation
  • River Street, West Kempsey - rehabilitation
    - restore driveways
    - prime seal Dangar Street to North Street, programmed for 9 June (weather permitting)
    - excavate and replace pavement at Elbow Street
  • North Street, West Kempsey - rehabilitation
    - install dish drain at Heyson Street
  • East Street, Crescent Head - rehabilitation
    - modify centre island and kerb ramps
    - asphalt overlay (weather permitting)
  • Entrance Street, South West Rocks - rehabilitation
    - excavate and replace pavement
  • River Street, West Kempsey - rehabilitation
    - driveway restoration
    Ongoing
    - heavy patching
    Completed between Leith Street and North Street
  • North Street, West Kempsey - rehabilitation
    - repairs weather damage to heavy patches
    - installation of sub-soil drains to prevent further damage to pavement from water ingress
  • East Street, Crescent Head - rehabilitation
    - asphalt wearing course installed at the roundabout and in East Street
    Works completed until September when a sprayed seal can be placed in East Street
  • Entrance Street, South West Rocks - rehabilitation
    Work on hold due to wet weather repairs.
  • River Street, West Kempsey - rehabilitation
    - restore driveways
    - primer seal Dangar Street to North Street complete
    - heavy patch between Short Street and Dangar Street
  • North Street, West Kempsey - rehabilitation
    - install dish drain at Heyson Street
    - primer seal heavy patches
  • East Street, Crescent Head - rehabilitation
    - modify centre island and kerb ramps
    - asphalt overlay (weather permitting)
  • Entrance Street, South West Rocks - rehabilitation
    - excavate and replace pavement
Gravel road re-sheeting
  • Willi Willi Road (Temagog Road to Toorumbee Road)
  • Willi Willi Road (Temagog Road to Toorumbee Road)
    50% complete
  • Willi Willi Road (Temagog Road to Toorumbee Road)
    - re-sheeting to complete
Gravel road maintenance grading
  • Willi Willi Road (with gravel re-sheeting)
    Collombatti Road
  • Willi Willi Road (with gravel re-sheeting)
    Collombatti Road

    Commenced
  • Point Plomer Road
    Work to commence
Roadside slashing
  • South West Rocks Road (Gladstone to South west Rocks)
  • No work due to water logged ground
  • South West Rocks Road (Gladstone to South west Rocks)
    Plummers Lane

    To commence
Other works
  • Waste Management Centre - new waste cell construction
    No work proposed - awaiting lining contractor
  • Frederickton streetscape
    Stage 3 - Chapman Street to shops (west side)

    - drainage works
    - line marking
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    - mulching
    - excavate and prepare base for major culvert
  • South West Rocks - PAMP
    Gregory Street

    - form and pour footpath
    Gregory Street/Frank Cooper Street
    - rebuild kerb ramps
  • Waste Management Centre - new waste cell construction
    No work proposed - awaiting lining contractor
  • Frederickton streetscape
    Stage 3 - Chapman Street to shops (west side)

    - drainage works
    95% complete - no progress (awaiting materials)
    - line marking
    Not started (too wet)
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthwork:
    - culvert excavation and ballast base
    Not started (too wet)
    - clearing and pegging for roadworks
    Ch0.00m to ch150m completed
  • South West Rocks - PAMP
    Gregory Street

    Kerb ramps:
    - old ramps and path removed
    Frank Cooper and Simpson intersections
    - ramps formed and poured
  • Gregory and Gordon Young Streets
    Pedestrian refuge, kerb and paths
    - kerb line pegged and materials prepared
  • Waste Management Centre - new waste cell construction
    No work proposed - awaiting lining contractor
  • Frederickton streetscape
    Stage 3 - Chapman Street to shops (west side)

    - drainage works
    - line marking scheduled in 2 weeks
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    - culvert excavation and ballast base to install
  • South West Rocks - PAMP
    Gregory Street

    Kerb ramps:
    - paths to complete at Frank Cooper and Simpson intersections
  • Gregory and Gordon Young Streets
    Pedestrian refuge, kerb and paths
    - retaining wall excavation and footing to complete

Further works information