Weekly works schedule
Week ending 5 July 2019

Proposed schedule this week Work achieved this week Proposed schedule next week
Bridge construction and maintenance
  • Turners Flat bridge replacement
    - installation of rock anchors
    - form piers
    - boring of piles (south side)
    - concreting of piles (south side)
  • Turners Flat bridge replacement
    - installation of rock anchors (north side)
    60% complete
    - form piers (north side)
    Commenced
    - boring of piles (south side)
    - concreting of piles (south side)
    Complete
  • Turners Flat bridge replacement
    - form piers (north side)
    - boring of two piles (midriver)
Flood mitigation maintenance
  • Killick Creek floodgates cells 3 & 4
    - remove gates - repair and refurbish
    - concrete cell repairs
  • Sillitoes Drain
    - wing wall anchor bolt
    - place headwall blocks
    - backfill
    - install concrete slab
    - handrail installation
  • Killick Creek floodgates cells 3 & 4
    - remove gates - repair and refurbish
    Delayed due to materials not arriving
    - concrete cell repairs
    50% complete
  • Sillitoes Drain
    - wing wall anchor bolt
    - place headwall blocks
    - backfill
    - install concrete slab
    Complete
    - handrail installation
    10% complete
  • Killick Creek floodgates cells 3 & 4
    - remove gates - repair and refurbish
    - concrete cell repairs
  • Sillitoes Drain
    - handrail installation
    - site clean-up
    - demobilise from site
Drainage/kerb/footpath maintenance and replacement
  • Horseshoe Bay Footpath (Stage 2)
    - seat - stone veneer
  • Horseshoe Bay Footpath (Stage 5)
    - form and pour footpath
  • Tozer Street, West Kempsey 
    (Marsh Street to Wide Street)

    - site setup
    - stormwater construction
  • Horseshoe Bay Footpath (Stage 2)
    - seat 1 - stone veneer
    50% complete
  • Horseshoe Bay Footpath (Stage 5)
    - form and pour footpath
    10% complete - delayed due to wet site conditions
  • Tozer Street, West Kempsey 
    (Marsh Street to Wide Street)

    - site setup
    Complete
    - stormwater construction
    2% complete
  • Horseshoe Bay Footpath (Stage 2)
    - seat 1- stone veneer - delayed due to contractor availability
  • Horseshoe Bay Footpath (Stage 5)
    - form and pour footpath
  • Tozer Street, West Kempsey 
    (Marsh Street to Wide Street)

    - stormwater construction
Bitumen road resealing/maintenance
  • South West Rocks streets
    South West Rocks Road
    Plummers Lane
    Smithtown Road
    Lachlan Street
    Crescent Head Road
    Gowings Hill Road
    Kempsey streets
    Sherwood Road
  • South West Rocks streets
    South West Rocks Road
    Plummers Lane
    Smithtown Road
    Crescent Head Road
    Kempsey streets
    Sherwood Road

    Complete
  • Lachlan Street
    - sealing
    Complete
  • Gowings Hill Road
    60% complete
  • Gowings Hill Road
    Armidale Road
Bitumen road construction and rehabilitation
  • Laurels Avenue
    - kerb and gutter
  • Gladstone Park
    - kerb and gutter
  • Gowings Hill Road
    - pipeline
    - tree removal and edging
    - shoulder widening
  • Laurels Avenue
    - kerb and gutter complete
  • Gladstone Park
    - kerb and gutter
    5% complete
  • Gowings Hill Road
    - pipeline
    20% complete - awaiting pipes
    - tree removal and edging
    Complete
    - shoulder widening
    30% complete
  • Laurels Avenue
    - form and pour dish drains
  • Gladstone Park
    - kerb and gutter
  • Gowings Hill Road
    - pipeline
    - shoulder widening
Gravel road maintenance grading
  • Hickeys Creek Road
    Mooneba Road
    Yessabah Road
    West End Road
    Sandy Creek Road
    Maria/Theresa Street
  • Hickeys Creek Road
    Mooneba Road

    50% complete
  • Yessabah Road
    Complete
  • West End Road
    Sandy Creek Road
    Maria/Theresa Street

    Deferred
  • Hickeys Creek Road
    Mooneba Road
    West End Road
    Sandy Creek Road
    Maria/Theresa Street
    Old Station Road
Roadside slashing
  • Armidale Road
    Smithtown area
    Gladstone area
  • Hat Head Road
    - vegetation control
  • Armidale Road
    90% complete
  • Smithtown area
    Gladstone area

    Complete
  • Hat Head Road
    - vegetation control
    To complete
  • Armidale Road
  • Hat Head Road
    - vegetation control
Projects/other works
  • Traffic islands/medians Shire-wide
    - spraying
  • Tree pruning Shire-wide
    - sight distance and clear carriageway
  • Verge Street, Kempsey
    Sports fields floodlights

    - installation of footings 
  • Jim Stirling Oval, South Kempsey
    Sports fields floodlights

    - installation of footings
  • Traffic islands/medians Shire-wide
    - spraying
    Ongoing
  • Tree pruning Shire-wide
    - sight distance and clear carriageway
    Ongoing
  • Verge Street, Kempsey
    Sports fields floodlights

    - installation of footings
    Complete
  • Jim Stirling Oval, South Kempsey
    Sports fields floodlights

    - installation of footings
    Delayed
  • Traffic islands/medians Shire-wide
    - spraying
  • Tree pruning Shire-wide
    - sight distance and clear carriageway
  • Verge Street, Kempsey
    Sports fields floodlights

    - trenching
  • Jim Stirling Oval, South Kempsey
    Sports fields floodlights

    - iInstallation of footings