Weekly works schedule
Week ending 17 November 2017

Proposed schedule this week Work achieved this week Proposed schedule next week
Bridge construction/maintenance
  • Nulla Nulla Creek Road - Bunghole Bridge
    Replacement:
    - clean up and disestablish
  • Nulla Nulla Creek Road - Bunghole Bridge
    Replacement:
    - clean up and disestablish
    Completed
  • No bridge works proposed
Flood mitigation maintenance
  • No flood mitigation maintenance proposed
  • Clybucca area
    - weed spraying
    Completed
  • Glenrock Drain
    - weed spraying
    25% complete
  • Glenrock Drain
    - weed spraying
Drainage/kerb/footpath/drainage maintenance and replacement
  • Gregory Street, South West Rocks (near shops)
    New kerb ramps and modify refuge:
    - form kerb ramps
    50% complete
    - remove median kerbs
    - form and pour median crossing
  • Gregory Street, South West Rocks (near shops)
    New kerb ramps and modify refuge:
    - form and pour kerb ramps
    - remove median kerbs
    - form and pour median crossing
  • West Kempsey area
    - remove and replace kerb and gutter
Bitumen road resealing/maintenance
  • Kempsey streets
    Fishermans Reach Road
    Gowings Hill Road
    Plummers Lane
    Goulds Lane

    - pothole patching
  • Kempsey streets
    - pothole patching
    Ongoing
  • Fishermans Reach Road
    – pothole patching
    Not started
  • Gowings Hill Road
    Plummers Lane
    Goulds Lane
    South West Rocks streets

    - pothole patching
    Completed
  • Kempsey streets
    Fishermans Reach Road
    Summer Island Road
    Aldavilla/Sherwood area
    Euroka area

    - pothole patching
Bitumen road construction/rehabilitation
  • Stuarts Point Road (Mighell Road to Browns Road)
    Widening and rehabilitation:
    - install guardrail
    - prepare for seal
  • South Street, South Kempsey
    Rehabilitation:
    - stabilise pavement
    - prepare for seal
  • Stuarts Point Road (Mighell Road to Browns Road)
    Widening and rehabilitation:
    - install guardrail
    50% complete
    - prepare for seal
    Completed
  • South Street, South Kempsey
    Rehabilitation:
    - stabilise pavement
    Completed
    - prepare for seal
    Commenced
  • Stuarts Point Road (Mighell Road to Browns Road)
    Widening and rehabilitation:
    - install guardrail
    - bitumen seal
  • South Street, South Kempsey
    Rehabilitation:
    - prepare for seal
    - bitumen seal
  • South West Rocks Road (Pola Creek Road to Red Hill Lane)
    - drainage works
Gravel resheeting
  • Jacks Crossing Road
    Rainbow Reach Road
    - place, spread and compact gravel
  • Jacks Crossing Road
    - place, spread and compact gravel
    80% complete
  • Rainbow Reach Road
    - place, spread and compact gravel
    Completed
  • Jacks Crossing Road
    - place, spread and compact gravel
Gravel road maintenance grading
  • Maria River Road
  • Maria River Road
    5% complete
  • Mines Road
    90% complete
  • Maria River Road
    Mines Road
    Mungay Creek Road
    Lukes Lane
Roadside slashing
  • Collombatti Road
    Kinchela area
    Belmore River area
    South Kempsey area
  • Collombatti Road
    Kinchela area
    Belmore River area
    Spooners Avenue

    Crottys Lane area
    Completed
  • South Kempsey area
    South West Rocks Road (Gladstone to Kempsey)
    50% complete
  • South Kempsey area
    South West Rocks Road (Gladstone to Kempsey)
    Armidale Road
Other works
  • Central Kempsey SewageTreatment Plant
    Access road and site earthworks:
    - earthworks to plant site
    - construct road pavement
  • Elbow Street upgrade (centre)
    - install islands
  • South Street - extension from West Street to Gowings Hill Road (contractor)
    - earthworks
    - provide rock bridging layer adjacent to culvert
  • Lachlan Street, South Kempsey (street upgrade)
    Stage 1 - West side (Carri Street to Nicholson Street):

    - excavate for kerb (1st section)
    - pour kerb (1st section)
    - construct footpath
  • Gregory Street (at Gordon Young Drive)
    Pedestrian refuge:
    - form and pour footpath (west side)
    - install kerb ramp (east side)
  • Willawarrin village area
    - reshape shoulder and improve drainage on southern side
  • Little Rudder Street
    Replace stairs to Macleay Valley Way:
    - install piers
  • Central Kempsey SewageTreatment Plant
    Access road and site earthworks:
    - earthworks to plant site
    Top pad completed
    - construct road pavement
    No progress
    - form roadside table drains
    Commenced
  • Elbow Street upgrade (centre)
    - install islands
    70% complete
  • South Street - extension from West Street to Gowings Hill Road (contractor)
    - earthworks
    15% complete
    - provide rock bridging layer at culvert
    No progress
  • Lachlan Street, South Kempsey (street upgrade)
    Stage 1 - West side (Carri Street to Nicholson Street)
    :
    - excavate for kerb (1st section)
    - pour kerb (1st section)
    - backfill kerb (1st section)
    Completed
    - construct footpath - place and compact fill
    Commenced
    - drainage works (2nd section)
    50% complete
  • Gregory Street (at Gordon Young Drive)
    Pedestrian refuge:
    - form and pour footpath (west side)
    - install kerb ramp (east side)
    Completed
  • Willawarrin village area
    - reshape shoulder and improve drainage on southern side
    Completed
  • Little Rudder Street
    Replace stairs to Macleay Valley Way:
    - install piers
    75% complete
  • Access to Back Creek Beach - South West Rocks Lions Club project (contractor)
    - excavation for ramp
    Completed
    - form and pour concrete ramp
    40% complete
  • Riverside Park wharf (contractor)
    - install bearers and joists
    Completed
    - install deck
    95% complete
  • East Kempsey Cemetery
    - bitumen seal internal road
    Completed
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    - earthworks to plant site (middle and bottom pads)
    - construct road pavement
    - form roadside table drains
    - trim batters
  • Elbow Street upgrade (centre)
    - install islands
  • South Street - extension from West Street to Gowings Hill Road (contractor)
    - earthworks
    - provide rock bridging layer at culvert
  • Lachlan Street, South Kempsey (street upgrade)
    Stage 1 - West side (Carri Street to Nicholson Street):

    - construct footpath
    - drainage works (2nd section)
  • Gregory Street (at Gordon Young Drive)
    Pedestrian refuge:
    - install handrail
    - install linemarking (subject to contractor availability)
  • Little Rudder Street
    Replace stairs to Macleay Valley Way:
    - install piers
    - construct stairs
  • Access to Back Creek Beach - South West Rocks Lions Club project (contractor)
    - form and pour concrete ramp
  • Riverside Park wharf (contractor)
    - install deck
    - install handrails

Further works information