Weekly works schedule
Week ending 22 September 2017

Proposed schedule this week Work achieved this week Proposed schedule next week
Bridge construction/maintenance
  • Various locations
    - routine bridge maintenance
  • Willi Willi Road - Quarry Bridge refurbishment
    - prepare girders/sills for replacement
  • Various locations
    - routine bridge maintenance
    Completed
  • Willi Willi Road - Quarry Bridge refurbishment
    - prepare girders/sills for replacement
    Completed
  • Willi Willi Road - Quarry Bridge refurbishment
    - remove deck
    - replace sills
    - replace girders
    - bridge to be closed for 3 weeks from 25 September
Flood mitigation maintenance
  • Anderson’s Drain
    - drain clearing
  • Anderson’s Drain
    - drain clearing
    Completed
  • No flood mitigation maintenance proposed
Drainage/kerb/footpath/drainage maintenance
  • Douglas Fentiman Street
    Greenfields Avenue
    Keith Dunn Street

    Kerb and gutter replacement:
    - excavate and prepare base
  • Gregory Street/Gordon Young Drive
    Pedestrian refuge:
    - asphalt crossing
  • Douglas Fentiman Street
    Kerb and gutter replacement:
    - excavate and prepare base
    Completed
  • Greenfields Avenue
    Kerb and gutter replacement:
    - excavate and prepare base
    Not started
  • Keith Dunn Street
    Kerb and gutter replacement:
    - excavate and prepare base
    50% complete
  • Gregory Street/Gordon Young Drive
    Pedestrian refuge:
    - place concrete median islands
    - asphalt crossing
    Planned for 22 September
  • Greenfields Avenue
    Keith Dunn Street
    Warwick Avenue

    Kerb and gutter replacement:
    - excavate and prepare base
  • Eden Street, Kempsey
    - replace damaged footpath
Bitumen road resealing/maintenance
  • Council carparks
    Priority works on town access roads

    - pothole patching
  • Council carparks
    - pothole patching
    Not started
  • Priority works on town access roads
    - pothole patching
    Completed
  • Council carparks
    Kempsey streets

    Pothole patching
Bitumen road construction/rehabilitation
  • Stuarts Point Road (Lukes Lane to Mighell Road)
    Widening and rehabilitation:
    - prepare for seal
    - bitumen seal
  • Stuarts Point Road (Mighell Road to Hunters Road)
    Widening and rehabilitation:
    - strip and prepare for widening
  • Elizabeth Street, South West Rocks (Gregory Street to Jubilee Street)
    - asphalt surfacing (weather permitting)
  • South Street, South Kempsey
    Rehabilitation:
    - pour kerb and gutter (remainder)
    - pour driveways (Mulvey)
    - excavate for pavement replacement
    - widen pavement (west of bridge)
    - pour driveways (north side)
  • Stuarts Point Road (Lukes Lane to Mighell Road)
    Widening and rehabilitation:
    - prepare for seal
    - initial bitumen seal
    Completed
  • Stuarts Point Road (Mighell Road to Hunters Road)
    Widening and rehabilitation:
    - strip and prepare for widening
    50% complete
  • Elizabeth Street, South West Rocks (Gregory Street to Jubilee Street)
    - asphalt surfacing
    Planned for 22 September
  • South Street, South Kempsey
    Rehabilitation:
    - pour kerb and gutter (remainder)
    - pour driveways (Mulvey)
    Not started (awaiting watermain relocation)
    - excavate for pavement replacement
    Commenced
    - widen pavement (west of bridge)
    - pour driveways (north side)
    Completed
  • Stuarts Point Road (Lukes Lane to Mighell Road)
    Widening and rehabilitation:
    - spot centreline
  • Stuarts Point Road (Mighell Road to Hunters Road)
    Widening and rehabilitation:
    - strip and prepare for widening
    - widen pavement
  • South Street, South Kempsey
    Rehabilitation:
    - excavate for pavement replacement
  • Wide Street, West Kempsey
    Rehabilitation:
    - rip, strengthen, trim and compact
Gravel resheeting
  • No gravel resheeting proposed

No gravel resheeting proposed

Gravel road maintenance grading
  • Carrai Road
    Spooners Avenue
    Frederickton Ferry Road
    Austral Eden Road
    Darkwater Street (Gladstone)
    Macleay Street (Gladstone)
  • Carrai Road
    30% complete
  • Spooners Avenue
    70% complete
  • Frederickton Ferry Road
    Austral Eden Road
    Darkwater Street (Gladstone)
    Macleay Street (Gladstone)

    Completed
  • Carrai Road
    Spooners Avenue
Roadside slashing
  • Macleay Valley Way (Kempsey to Gladstone)
    - additional work with reach mower
  • Macleay Valley Way (Frederickton to Stuarts Point Road)
    -
    additional work with reach mower
    60% complete - no progress (plant breakdown)
  • South West Rocks Road (Kempsey to Gladstone)
    Completed
  • Kundabung area
Other works
  • Waste Management Centre
    New waste cell construction:
    - repair damaged leachate collection pipes and liner
    - install drainage layer
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    - earthworks to plant site
    - clearing south-west boundary
    - stripping revised road alignment
  • Elbow Street upgrade (south side)
    - install paver bands at Argus
    - pour kerb and gutter (Governmentt offices)
    - form and pour remaining footpaths
  • Elbow Street upgrade (north side)
    - prepare for kerb
    - pour kerb
  • Tozer Street - roundabout at Elbow Street
    - form and pour centre wall
    - form and pour apron
  • Waste Management Centre
    New waste cell construction:
    - repair damaged leachate collection pipes and liner
    Completed
    - install drainage layer
    80% complete
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthwork:
    - earthworks to plant site
    40% complete
    - clearing south-west boundary
    Completed
    - stripping revised road alignment
    Continuing
  • Elbow Street upgrade (south side)
    - install paver bands at Argus
    - pour kerb and gutter (Goverment offices)
    - form and pour remaining footpaths
    Completed
  • Elbow Street upgrade (north side)
    - prepare for kerb
    Completed
    - pour kerb
    90% complete
  • Tozer Street - roundabout at Elbow Street
    - pour centre wall
    - form and pour apron
    Completed
  • Waste Management Centre
    New waste cell construction:
    - install drainage layer
  • Central Kempsey Sewage Treatment Plant
    Access road and site earthworks:
    - earthworks to plant site
    - stripping revised road alignment
  • Elbow Street upgrade (south side)
    - seal shoulder
    - tidy up grassed areas
  • Elbow Street upgrade (north side)
    - pour kerb
    - convert to centre parking
  • Tozer Street/Marsh Street intersection
    - excavate and replace failed pavement

Further works information