Weekly works schedule
Week ending 25 May 2018

Proposed schedule this week Work achieved this week Proposed schedule next week
Bridge construction/maintenance
  • Nulla Nulla Creek Road - McIntyres Bridge replacement (contract)
    - install deck units
  • Schmidts Road - Schmidts Bridge replacement (contract)
    - install abutment sheeting
    - install headstocks
  • Kinchela Creek Left Bank Road - Knauers Bridge replacemeent
    - restore approaches
    - install guardrail to approaches
  • Nulla Nulla Creek Road - McIntyres Bridge replacement (contract)
    - install deck units
    - install wing walls
    Completed
  • Schmidts Road - Schmidts Bridge replacement (contract)
    - install abutment sheeting
    Completed
    - install headstocks
    Commenced
  • Kinchela Creek Left Bank Road - Knauers Bridge replacement
    - restore approaches
    - install guardrail to approaches
    Not started
  • Nulla Nulla Creek Road - McIntyres Bridge replacement (contract)
    - install kerbs
    - construct road approaches
  • Schmidts Road - Schmidts Bridge replacement (contract)
    - install headstocks
  • Kinchela Creek Left Bank Road - Knauers Bridge replacement
    - restore approaches
    - install guardrail to approaches
Flood mitigation maintenance
  • No works proposed
  • No works undertaken
  • No works proposed
Drainage/kerb/footpath maintenance and replacement
  • Michael Place, South West Rocks
    Stormwater pipe defect rectification:
    - pour footpaths
    - form pedestrian ramps
  • Memorial Avenue, Kempsey
    Replace failed kerb and gutter:
    - pour kerb and gutter
  • George Hardiman Avenue, West Kempsey
    Replace failed kerb and gutter:
    - pour kerb and gutter
  • Frank Archibald Street, Greenhill
    Replace failed kerb and gutter:
    - pour kerb and gutter
  • Michael Place, South West Rocks
    Stormwater pipe defect rectification:
    - pour footpaths
    80% complete
    - form pedestrian ramps
    Not started
  • Memorial Avenue, Kempsey
    Replace failed kerb and gutter:
    - pour kerb and gutter
    Completed
  • George Hardiman Avenue, West Kempsey
    Replace failed kerb and gutter:
    - pour kerb and gutter
    Completed
  • Frank Archibald Street, Greenhill
    Replace failed kerb and gutter:
    - pour kerb and gutter
    Completed
  • Michael Place, South West Rocks
    Stormwater pipe defect rectification:
    - pour footpaths
    - form and pour pedestrian ramps
  • Memorial Avenue, Kempsey
    Replace failed kerb and gutter:
    - backfill and restore pavement
  • George Hardiman Avenue, West Kempsey
    Replace failed kerb and gutter:
    - backfill and restore pavement
  • Frank Archibald Street, Greenhill
    Replace failed kerb and gutter:
    - backfill and restore pavement
Bitumen road resealing/maintenance
  • Spooners Avenue
    Yarravel area
    Armidale Road, Willawarrin

    - pothole patching
  • Spooners Avenue
    Yarravel area
    Armidale Road, Willawarrin

    - pothole patching
    Completed
  • Kundabung area
    Gowings Hill Road
    Marys Bay Road

    - pothole patching
Bitumen road construction/rehabilitation
  • Tozer Street (Elbow Street to Marsh Street)
    - construct permanent concrete median islands
  • Tozer Street (Elbow Street to Kemp Street) - east side
    - remove failed kerb and gutter
    - pour kerb and gutter
    - excavate and place subbase
    - restore driveways
  • Plummers Lane (Macleay Valley Way to 1.2km)
    Rehabilitation:
    - extend pipe culverts
    - strip vegetation/soil from shoulders
  • Sherwood Road (Ronella Drive to Hillview Drive)
    Rehabilitation:
    - prepare for seal
    - bitumen seal
  • Tozer Street (Elbow Street to Marsh Street)
    - construct permanent concrete median islands
    90% complete
  • Tozer Street (Elbow Street to Kemp Street) - east side
    - remove failed kerb and gutter
    - pour kerb and gutter
    20% complete
    - excavate and place subbase
    Completed
    - restore driveways
    Completed to Edinburgh Lane
  • Plummers Lane (Macleay Valley Way to 1.2km)
    Rehabilitation:
    - extend pipe culverts
    30% complete - no progress
    - strip vegetation/soil from shoulders
    Not started
  • Sherwood Road (Ronella Drive to Hillview Drive)
    Rehabilitation:
    - prepare for seal
    Completed
    - bitumen seal
    Planned for 25 May
  • Tozer Street (Elbow Street to Marsh Street)
    - construct permanent concrete median islands
  • Tozer Street (Elbow Street to Kemp Street) - east side
    - remove failed kerb and gutter
    - prepare for new kerb and gutter
  • Plummers Lane (Macleay Valley Way to 1.2km)
    Rehabilitation:
    - extend pipe culverts
    - strip vegetation/soil from shoulders
  • Sherwood Road (Ronella Drive to Hillview Drive)
    Rehabilitation:
    - bitumen seal
Gravel resheeting
  • No gravel resheeting proposed
  • McCarthys Lane
    (by opportunity from Macleay Valley Way asphalt works)
    Completed
  • Menarcobrinni Road
    20% complete
  • Menarcobrinni Road
Gravel road maintenance grading
  • Beranghi Road
    Five Day Creek Road
    Smiths Creek Road
    Wortley Drive
    Mooneba Road
  • Beranghi Road
    Smiths Creek Road
    Wortley Drive
    Belmore River Right Bank Road

    Completed
  • Five Day Creek Road
    50% complete
  • Mooneba Road
    Not started
  • Five Day Creek Road
    Mooneba Road
    Airport Road
    Warneton Road
Roadside slashing
  • Plummers Lane
    Armidale Road
    Hickeys Creek Road
    Stuarts Point Road
    Grassy Head Road
    Macleay Valley Way (south)
    West Kempsey area
  • Armidale Road
    Hickeys Creek Road
    Grassy Head Road
    Macleay Valley Way (south)

    Completed
  • West Kempsey area
    70% complete
  • Plummers Lane
    Not started
  • Stuarts Point Road
    50% complete
  • Plummers Lane
    Stuarts Point Road
    West Kempsey area
    Macleay Valley Way (north to Frederickton)
Other works
  • Lachlan Street, South Kempsey
    (Nicholson Street to Yarravel Street - west side)

    - drainage works
    - pour footpaths and pram ramps
    - set out for new kerb and gutter
  • Macleay Valley Way (Bellimbopinni)
    Concrete pavement repairs:
    - remove and replace failed concrete pavement
  • Macleay Valley Way (Bellimbopinni to Plummers Lane)
    Shoulder replacement:
    - mill existing sealed shoulders and replace with asphalt
  • Lachlan Street, South Kempsey
    (Nicholson Street to Yarravel Street - west side)

    - drainage works
    75% complete
    - form and pour footpath adjacent bottle shop
    - set out for new kerb and gutter
    - pour kerb and gutter adjacent bottle shop
    Completed
  • Macleay Valley Way (Bellimbopinni)
    Concrete pavement repairs:
    - remove and replace failed concrete pavement
    25% complete
  • Macleay Valley Way (Bellimbopinni to Plummers Lane)
    Shoulder replacement:
    - mill existing sealed shoulders and replace with asphalt
    20% complete
  • Lachlan Street, South Kempsey
    (Nicholson Street to Yarravel Street - west side)

    - drainage works
    - backfill kerb and verge
    - form and pour driveway to bottle Shop
    - form concrete slab fronting bottle shop
    - form half layback to Caltex.
  • Macleay Valley Way (Bellimbopinni)
    Concrete pavement repairs:
    - remove and replace failed concrete pavement
  • Macleay Valley Way (Bellimbopinni to Plummers Lane)
    Shoulder replacement:
    - mill existing sealed shoulders and replace with asphalt