Elbow Street, West Kempsey - proposed roadworks
23 June 2017

Roadworks in Elbow Street, West Kempsey are planned to commence on 26 June (weather permitting). The work involves replacement of water mains, kerb and gutter, some footpaths, replacement of the road pavement, bitumen sealing and conversion to centre parking west of Tozer Street with tree planting and associated landscaping. The work will require the use of earthmoving plant and trucks and is expected to take six weeks.

During the work vehicle access to properties may be restricted intermittently. Traffic control will be in place as required and every effort will be made to maintain access to businesses. Motorists are requested to follow instructions from traffic controllers at all times. To avoid delays alternative routes should be considered where possible.

Council appreciates the cooperation and support of local residents while the works are carried out. For further information please contact the Customer Service Centre on 6566 3200


Entrance Street, South West Rocks - roadworks delayed
Update No. 1 - 23 June 2017

Roadworks in Entrance Street, South West Rocks have been delayed by recent wet weather. Work is now expected to commence on 26 June. The work involves ripping and strengthening of the road pavement, bitumen sealing and associated works. It will require the use of earthmoving plant and trucks and is expected to take two weeks.

During the work vehicle access to properties may be restricted intermittently. Traffic control will be in place as required. Residents are requested to follow instructions from traffic controllers at all times. To avoid delays alternative routes should be considered where possible.

Council appreciates the cooperation and support of local residents while the works are carried out. For further information please contact the Customer Service Centre on 6566 3200


River Street, West Kempsey - roadworks in progress
Update No. 6 - 5 June 2017

Roadworks in River Street, West Kempsey between North Street and Elbow Street are progressing. The current worksite is from North Street to Dangar Street. The remaining work involves stabilisation, bitumen sealing and associated works. It will require the use of earthmoving plant and trucks.

During the work access to properties may be restricted intermittently. Traffic control will be in place as required and a temporary speed limit may be enforced. Short delays will be encountered. Residents are requested to obey the speed limit and follow instructions from traffic controllers at all times. Alternative routes should be considered.

Council appreciates the cooperation and support of local residents while the works are carried out. For further information please contact the Customer Service Centre on 6566 3200


North Street, West Kempsey - roadworks in progress
Update No. 3 - 10 May 2017

Roadwork in North Street, West Kempsey between River Street and Tozer Street has re-commenced. The work involves excavation and replacement of failed sections of the kerb and gutter and road pavement, bitumen sealing and associated works. It will require the use of earthmoving plant and trucks and is expected to take three weeks. During the work access to properties may be restricted intermittently.

Traffic control will be in place as required and a temporary speed limit may be enforced. Residents are requested to obey the speed limit and follow instructions from traffic controllers at all times.

Council appreciates the cooperation and support of local residents while the works are carried out. For further information please contact the Customer Service Centre on 6566 3200


Changed traffic conditions - Smiths Creek Road intersection closure
2 May 2017

Roads & Maritime Services advise that the intersection of Smiths Creek Road and the Pacific Highway will permanently close from early May 2017, weather permitting.

The closure of the intersection at Smiths Creek Road and the highway will allow the northbound on-ramp of the Kundabung interchange and the new northbound carriageway to be completed.

Northbound access to the local roads will be via the Kundabung interchange off-ramp. The exit will be about one kilometre prior to the existing Smiths Creek Road intersection. Electronic message boards and additional signage will be provided to assist motorists. A map is attached showing the planned traffic changes.

Motorists wishing to travel north to Kempsey from this area will detour via Rodeo Drive and Ravenswood Road (old highway alignment) and travel about seven kilometres and re-join the highway.

Bus operations will continue to use the bus stop at the Kundabung Motel on Smiths Creek Road during this time.